CONSTRUCTION PHASING

Phase

Description
Click on a phase to see the traffic configuration.

1

Northbound and southbound I-95 outside lanes will be milled and resurfaced and traffic will be diverted to the inside lane, (one thru-lane each direction).

2

Northbound and southbound I-95 middle lanes will be milled and resurfaced and traffic will remain diverted to the inside lane, (one thru-lane each direction).

3

Northbound and southbound traffic will be diverted to the newly constructed outside lane while the inside lane is milled and resurfaced.