CONSTRUCTION PHASING

Phase

Description
Click on a phase to see the traffic configuration.

Start Date

Completion

1

Noise walls along both sides of I-95 will be constructed in this phase. Traffic will be shifted towards the outside of the existing roadway to accommodate the temporary road and bridge construction in the existing median.

November, 2002

October, 2003

2

Southbound traffic will be diverted to the newly constructed median area as the road and bridge improvements on the southbound side of I-95 are constructed.

November, 2003

Spetember, 2004

3

Northbound traffic will be diverted to the previously constructed median and the southbound traffic will be on the newly constructed southbound roadway area as the road and bridge improvements on the northbound side of I-95 are constructed.

October, 2004

July, 2005

4

Complete the construction of the road and bridge improvements in the median as northbound and southbound traffic use the newly constructed roadways.

August, 2005

August, 2006

5

Traffic will be shifted into its final configuration as the roadway is resurfaced.

August, 2006

September, 2006