 |
Project
Limits |
|
I-95 from north of Palm Beach
Lakes Blvd.
To north of Blue Heron Blvd. |
 |
Purpose |
|
Improve roadway capacity, safety
and efficiency. |
 |
Scope of Work |
|
FDOT is widening
I-95 from six lanes to ten lanes along this section, a length of approximately
4.58 miles. The work includes widening the existing bridge over SR 710,
replacing the existing bridges over 45th Street and Blue Heron
Blvd., and reconstructing the mainline ramps. The project will also include drainage improvements,
sound barrier walls, retaining walls, signing and pavement marking, lighting,
landscaping, irrigation and communications elements. |
 |
Construction Timeline |
|
Begin Construction: November
2004
End Construction: April 2008 |
 |
Maintenance of Traffic |
|
Lane closures on I-95 will only
occur at night when traffic volumes are lighter. Three thru lanes will
be maintained at all times from 5:30 am to 8:00 pm.
No ramp closures will be required on this section of I-95.
Lane closures on 45th Street and
Blue Heron Blvd. will only occur at night when traffic volumes are lighter
for the demolition of the existing bridges, installation of pilings, and
when it is necessary to ensure the safety of the traveling public. |
 |
Construction Phasing |
| |
Phase
I |
| |
I-95
will be milled and resurfaced and outside shoulder slope correction will
be completed. 45th Street,
SR 710, and Blue Heron Blvd. will have temporary asphalt installed for
use in future phases. |
| |
Phase
II |
| |
Traffic
will be shifted to the outside of the existing roadway to accommodate
the temporary road and permanent bridge construction in the median. |
| |
Phase
III |
| |
Traffic
will be shifted towards the newly constructed median area as the road
and bridge improvements on I-95 are constructed. Widening will be done on 45th Street
and Blue Heron Blvd. |
| |
Phase
IV |
| |
Traffic
will be shifted towards the previously constructed median area as the
road and bridge improvements on I-95 are constructed. SR 710 will be restored to its original condition. |
| |
Phase
V |
| |
Traffic
will be shifted towards the median area as the road and bridge improvement
on I-95 are constructed. |
| |
Phase
VI |
| |
Traffic
will be shifted towards the outside as the construction of the road in
the median is completed. Roadwork
on 45th Street and Blue Heron Blvd. will be completed in this
phase. |
 |
Factoids |
|
Over 1.3 million pounds of steel
and 8 million pounds of concrete will be used to build three bridges.
Over 300 miles of temporary and permanent striping will be used on this
project—enough to reach from West Palm Beach to the Georgia state
line!
Over 150,000 tons of asphalt will be used on this project—the
same weight as 1,000 blue whales!
|