Phase
Description Click on a phase to see the traffic configuration.
Start Date
Completion
1
SR 80. Traffic will be shifted to the outside. Remove all traffic separators and place temporary asphalt in the median. Construct Airport Center west entrance. I-95. Traffic will be reduced to three lanes in each direction and maintained on the existing roadway while work is being done on the shoulders and in the median. Three of the four ramps will be reduced to one lane as construction begins.
March, 2004
April, 2004
2
SR 80. Shift westbound traffic to the newly constructed median pavement. Construct new westbound lanes. Demolish and reconstruct westbound bridges over Stub Canal and I-95. I-95. Traffic will be switched between the northbound and southbound lanes as needed for bridge work being done above. Three lanes of traffic will be open in each direction. Ramp work will continue on all four ramps. Temporary concurrent ramp closures on the southbound I-95 to SR 80 off-ramp and SR 80 to northbound I-95 on-ramp will be made as the connections to SR-80 are being constructed.
May, 2005
3
SR 80. Shift traffic to the newly constructed westbound pavement. Construct new eastbound lanes. Demolish and reconstruct eastbound bridges over Stub Canal and I-95. I-95. Traffic will be switched between the northbound and southbound lanes as needed for bridge work being done above. Three lanes of traffic will be open in each direction. Ramp work will continue on all four ramps. Temporary concurrent ramp closures on the northbound I-95 SR 80 off-ramp and SR 80 to southbound I-95 on-ramp will be made as the connections to SR-80 are being constructed.
March, 2006
4
SR 80. Traffic will be shifted to the outside of the newly constructed lanes while the median is constructed. I-95. Traffic will be restored to four lanes in each direction as the road is being milled and resurfaced.
October, 2006