| FIN # 231835-1-52/56-01, 231919-1-52-01 |
|||||
Federal Aid #0951 564 I, 0951 567 I |
|||||
| From south of SR 80 |
|||||
| Description of Work: |
|||||
| Contractor
|
Andres
Lozano |
Letting |
10/30/02 |
Contract |
T4002 |
| Resident Engineer |
Eduardo Perez de Morales,
P.E. |
Award |
12/13/02 |
Construction Time |
1009 CD |
| FDOT Project Manager |
Geoffrey Parker,
P.E. |
Executed |
01/13/03 |
Contract Amount |
$34,362,394.68 |
| Project Engineer |
Rowan Carter,
P.E. |
NTP |
02/11/03 |
Earned to Date |
$34,251,490.32 |
| Design Project Engineer |
John Thompson,
P.E. |
Begin Construct. |
03/08/04 |
Estimated Completion |
10/04/06 |
| Design
Firm |
Murray Thornburg,
P.E. |
Contract Completion |
10/04/06 |
Number of Days Used |
941 |
| Special Considerations: No Excuse Bonus: Bonus #1: $1,750,000 Complete all contract work and obtain acceptance
in 848 days. Other Special Provisions:
Article 7-11.3.1: Hauling and staging: Prohibits the contractor to stage and/or haul material and equipment using local surface streets. Access to the project’s work zone shall be directly from I-95. Article 8-3.3: Prosecution of Work- Flexible Start Time: Allows the contractor to procure material. It requires the contractor to obtain an approved schedule. Trainee requirements are identified and a trainee schedule is submitted and approved by the Department. Submittal of all critical shop drawings and attend a mandatory constructability workshop. Article 8-3.7: Disputes Review Board: The Board will provide special expertise to assist in and facilitate the timely and equitable resolution of disputes, claims, and controversies between the Department and the Contractor in an effort to avoid construction delay and future claims. Article 8.4-10: Protection of Adjacent Properties: Any equipment
used by the Contractor for this project shall not exceed vibration levels
of 5 mm per second at any point within 125 m of the right of way. The
Contractor shall employ a qualified Specialty Engineer to monitor and
record vibration levels produced by vibratory construction equipment used
on this project. The Contractor shall perform a Pre-Construction survey with the use
of video and still photography on each property, located within 125 m
from the Right of Way, identifying the existing structural conditions,
of the property or any other improvement of such property which may be
affected by vibration. Article 8-4.11: Noise Restrictions: Contractor’s working hours generating noise above 50dba are restricted as follows: M-F 8:00 AM- 7:00 PM, Saturday 10:00 AM - 8:00 PM and no work is allowed on Sundays. |
|||||