Project
Limits |
|
I-95 from 10th Avenue North to south of Southern Boulevard (SR 80) |
 |
Purpose |
|
Improve roadway capacity, safety and efficiency. |
 |
Scope of Work |
|
FDOT is widening I-95 from six lanes to ten lanes along this section,
a length of approximately 2.94 miles. The work includes widening the existing
bridges over 17th Avenue North, Forest Hill Boulevard, and Summit Boulevard,
replacing the existing bridge over the C-51 Canal, and reconstructing
the mainline ramps. The project
will also include drainage improvements, sound barrier walls, retaining
walls, signing and pavement marking, lighting, landscaping, irrigation,
and communications elements. |
 |
Construction
Timeline |
|
Begin Construction: January 2004
End Construction: March 2008 |
 |
Maintenance
of Traffic |
|
Lane closures on I-95 will only occur at night when traffic volumes are
lighter. Three thru lanes will
be maintained at all times from 5:30 am to 8:00 pm. There will also be ramp closures as follows:
Southbound I-95 to 10th Avenue North off-ramp
– 28 days
10th Avenue North to Northbound I-95 on-ramp – 35 days
Northbound I-95 to Forest Hill Boulevard off-ramp – 9 days
Advance warning of ramp work will be provided. |
 |
Construction Phasing |
|
Phase I |
|
10th Avenue North to North of Forest Hill Boulevard. Noise walls along
the east sides of I-95 will be constructed in this phase. Traffic will be shifted towards the outside
of the existing roadway to accommodate the temporary road construction
in the median, and inside widening of the 17th Avenue North, C-51 Canal,
and Forest Hill Boulevard bridges. |
|
Phase II |
|
10th Avenue North to North of Forest Hill Boulevard. Southbound traffic
will be diverted to the newly constructed median area as the road and
bridge improvements on the southbound side of I-95 are constructed. |
|
Phase III |
|
10th Avenue North to North of Forest Hill Boulevard. Northbound traffic will be diverted to the
previously constructed median, and the southbound traffic will be on the
newly constructed southbound roadway area as the road and bridge improvements
on the northbound side of I-95 are constructed. |
|
Phase IV |
|
10th Avenue North to North of Forest Hill Boulevard. Complete the construction of the road in the
median as northbound and southbound traffic use the newly constructed
roadway.
North of Forest Hill Boulevard to South of Southern Boulevard. Median bridge widening will be done at the
Summit Boulevard bridge. |
|
Phase V |
|
North of Forest Hill Boulevard to South of Southern Boulevard. Complete the construction of the road in the
median as northbound and southbound traffic is shifted towards the outside
of the existing roadway. |
|
Phase VI |
|
Traffic will be shifted to its final configuration as the roadway is
resurfaced. |
 |
Factoids |
|
Over 160 million pounds of asphalt will be
used on this project.
Over 16,800 yards of temporary and permanent barrier wall will be used.
That’s equivalent to 168 football fields!
Over 215 miles of permanent and temporary striping will be used—enough
to reach from West Palm Beach to Key West!
|