| FIN #231918-1-52-01/02 |
|||||
| Federal Aid #0951 568 I |
|||||
From 12th Avenue S. |
|||||
| Description of Work: |
|||||
| Contractor |
Mike
Nash (954) 931-9786 |
Letting |
12/03/03 |
Contract |
T4039 |
| Resident Engineer |
Eduardo Perez
de Morales, P.E. |
Award |
01/16/04 |
Construction Time |
1113CD |
| FDOT Project Manager |
Courtney Drummond,
P.E. |
Executed |
02/05/04 |
Contract Amount |
$58,830,990.14 |
| Project
Engineer |
Robert Audette, P.E |
NTP |
03/05/04 |
Earned to Date |
$57,614,872.68 |
| Design Project Engineer |
Henry Oaikhena, P.E. henry.oaikhena@dot.state.fl.us (954) 777-4445 |
Begin Construct. |
07/06/04 |
Date Completed |
05/02/2008 |
| Design
Firms |
Larry Low, P.E (813) 282-2349 |
Contract Completion |
07/23/2007 |
Number of Days Used |
1397 |
| Special
Considerations: No Excuse Bonus: Bonus #1: $2,000,000 Complete all contract work and obtain acceptance
in 1000 days. Incentive/Disincentive: Project: I/D daily amount of $10,000. Maximum I/D: $300,000; 1000 Calendar
Days from commencement of Contract Time. Other Special Provisions: Article 7-11.3.1: Hauling and staging: Prohibits the contractor from parking, staging and/or hauling material and equipment using local surface streets except for the construction of the Lake Worth High School parking lots. Article 8-3.3: Prosecution of Work- Mandatory Start: Contract Time will start on July 6, 2004. The Contractor will use the time from Notice to Proceed to July 6, 2004 to procure and fabricate materials, for the submittal and review of shop drawings, for the submittal and review of the schedule, to participate in a Constructability/Value Engineering Workshop, and to adjust work forces, equipment and schedules to proceed in a manner to minimize disruption to the public. Article 8-3.7: Disputes Review Board: The Board will provide special expertise to assist in and facilitate the timely and equitable resolution of disputes, claims, and controversies between the Department and the Contractor in an effort to avoid construction delay and future claims. Article 8-4.1.1: Sequence of Operations: Lake Worth High School Parking Improvements: The Lake Worth High School Parking Improvements will begin July 6th, 2004 and shall be completed in their entirety prior to September 15th, 2004. No other work under the contract shall begin until the Lake Worth High School Parking Improvements are completed and accepted by the Engineer. The Contractor shall not use the area of the Lake Worth High School Parking Improvements for staging, parking or any other purpose after completion and partial acceptance of that work. Ground-Mounted Sound Barrier Walls: The Ground-Mounted Sound Barrier Walls included in this contract shall be constructed and completed in Phase 1 of this contract. No work designated in the Traffic Control Plans as part of Phase 2 shall begin until the Ground-Mounted Sound Barrier Walls have been completed. Traffic Control Plan Phasing: The Contractor shall focus his efforts and schedule his work forces to expedite completion of Ramp 2A1 within the first 25 days of Phase 2, completion of Ramp 1A1 within the first 155 days of Phase 2, and completion of Ramp 1D1 within the first 200 days of Phase 2. The Contractor shall focus his efforts and schedule his work forces to expedite completion of Ramp 1B1 within the first 125 days of Phase 3. The Contractor shall not begin work on Ramp 1C1 until completion of the ramp becomes critical in the Contractor’s schedule. This phasing is being done in order to minimize the duration of ramp closures. Staged HOV Lane Opening and Coordination: The Department desires to open new HOV lanes in a manner that ensures segments of suitable length are opened at the earliest practical opportunity. HOV lanes from Lantana Road to South of SR 80 are expected to open in June of 2007. Article 8.4-10: Protection of Adjacent Properties: Any equipment
used by the Contractor for this project shall not exceed vibration levels
of 0.20 inch per second at any point within 100 feet of the right of
way. The Contractor shall employ a qualified Specialty Engineer to monitor
and record vibration levels produced by vibratory construction equipment
used on this project. The Contractor shall perform a Pre-Construction
survey with the use of video and still photography on each property,
located
within 400 feet from the Right of Way, identifying the existing structural
conditions, of the property or any other improvement of such property
which may be affected by vibration. In addition, a limit of 1000 feet
will be used to monitor vibration levels around Lake Worth High School
and the City of Lake Worth Water and Electric facilities. Article 8-4.11: Noise Restrictions: Equivalent sound levels shall not exceed 50dba Monday - Friday from 8 p.m. to 8 a.m., all day Sunday and during legal holidays.
|
|||||